Type Tests of Gas Insulated Switchgear
- Power Frequency Withstand Test
- Lightning Impulse Voltage Withstand Test
- Switching Impulse Voltage Withstand Test
- Making and Breaking Capability Tests
- Continuous Current Carrying and Temperature Rise Tests
- Resistance Measurement of Current Carrying Parts
- Mechanical Tests
- Partial Discharge Tests
Routine Tests on Gas Insulated Switchgear (GIS)
The below mentioned tests are performed on complete GIS assembly
- Power Frequency Voltage Withstand Tests on Main Circuit
- Partial Discharge Measurement
- Measurement of Resistance of Main Circuit
- Gas Tightness Test
Below mentioned tests are performed on the individual equivalent like
Circuit Breaker:
- Mechanical Operation Test of Circuit Breaker
- Dielectric Tests of Auxiliary and Control Circuit of Circuit Breaker
- Functional Tests of Auxiliary Circuits, Auxiliary Equipment and Interlocks of Circuit Breaker.
Current Transformer:
- Visual Verification of Rating Plates and Terminal Markings
- Polarity and Ratio Tests
- Measurement of CT Resistance, Excitation Current & Knee Point Voltage
Potential Transformer:
- Visual Verification of Rating Plates and Terminal Marking
- Measurement of Polarities and Ratio
Disconnectors/Isolators:
- Mechanical Operation Test
- Dielectric Tests on Auxiliary and Control Circuits
- Test on Auxiliary Circuit, Control Circuit & Auxiliary Equipment
Acceptance Tests of Gas Insulated Switchgear
The acceptance tests are the same as factory routine tests.